Cost is a central issue in the ongoing debate about the best approach to building Australia’s National Broadband Network (NBN). Let’s find out the real cost of the network in its current iteration.
Fibre picture from Shutterstock
Rod Tucker is a Laureate Emeritus Professor at the University of Melbourne
In 2013, the Coalition argued that Labor’s original all-fibre to the premises (FTTP) network could cost as much as $94 billion. In the 2016 NBN Corporate plan the figure was revised down to $74 billion to $84 billion, while NBN Co’s multi technology mix (MTM), incorporating fibre to the node (FTTN) and upgraded hybrid fibre coax (HFC) was less costly, with a price tag of $46 billion to $56 billion.
Since the Coalition announced these numbers, Labor has said that, if elected, it will not go back to an all-FTTP network, but instead pursue a half-way option, in which the HFC component of the MTM is retained but FTTN, the slowest and most limited technology, is phased out.
It’s worth looking more closely at cost difference between FTTP and FTTN to see if the claimed $84 billion to $56 billion maximum cost comparison stacks up, and see where Labor’s new half-way solution sits.
Capital costs
The NBN 2016 Corporate Plan states that the average capital cost (capex) to connect a home or business to the NBN using FTTP is $3,700. But the real cost for a FTTP connection is probably less than this.
The $3,700 figure quoted by nbn co is based on old construction techniques that have been superseded in other parts of the world. The costs of rolling-out FTTP in New Zealand, for example, have been dropping steadily in recent years and will soon be $2,900 per premises. For some reason, NBN Co has yet to acknowledge the lessons learned in New Zealand.
Let’s give NBN Co the benefit of the doubt and assume that the $3,700 cost per premises for FTTP is correct. In comparison, the 2016 Corporate Plan states that the average capital cost for a FTTN connection is $1,600, or $2,100 less than FTTP.
For an upgraded hybrid-fibre-coax (HFC) connection the capital cost is $1,100, or $2,600 less. However, in light of recent revelations in a leaked document from NBN Co published by Fairfax indicating that it may be necessary to overbuild Optus’ HFC network, the savings offered by HFC will not be as good.
Using these numbers, it is easy to compare the capital costs of different networks.
At the end of construction, the MTM network will provide FTTN to 4.5 million premises and HFC to 4 million premises. Labor’s new approach is to replace as many as possible of these 4.5 million FTTN connections by FTTP. The maximum additional capital cost to do this would be 4.5 million times $2,100, or $9.5 billion. This figure corresponds to $790 per premises averaged across all 12 million premises in Australia.
An all-FTTP network could be achieved by also replacing the HFC connections with FTTP. The total additional capital cost of this hypothetical all-FTTP network would be $19.9 billion, or $1,658 per premises averaged across all premises.
Peak funding
Of course, it is necessary to also consider operational expenditure (opex) – the cost of running the network – and revenues from the network. These factors all contribute to the peak funding figures in the 2016 Corporate Plan.
Peak funding is the maximum cash outlay required before cash flow becomes positive. Peak funding is a useful measure of cost because it is a direct measure of the cash outlay required. But it is not necessarily a good measure of the cost of the network infrastructure or a good measure of the net financial cost/benefit to the Australian taxpayer.
Operational expenditure is a major issue for the MTM network because of factors including the need for new software management systems, the additional costs of maintaining the degrading copper wires in the FTTN network, and the cost of the electricity required to power the FTTN nodes located in suburban streets. Importantly, an FTTP network would incur none of these costs.
In fact, the leaked nbn co document mentioned earlier shows that the operational costs of FTTN network are 67% more than for FTTP, and the operational costs of HFC are 25% more. Over the lifetime of the network, this difference could amount to billions of dollars, greatly reducing the overall difference in costs between FTTN and FTTP.
Another factor that reduces the cost difference between the Coalition’s network and Labor’s new alternative is that a Labor’s FTTP/HFC network would be capable of generating higher revenues through the delivery of premium services that would not be achievable with a slower-speed FTTN network.
This is well documented by high-profile companies such as Ovum, which predicts FTTP services will drive the highest global growth rates for broadband revenues over the next five years, based on premium speeds of 100 Mbps and higher.
Timeframes
In light of all these factors, why is NBN Co’s cost estimate for a hypothetical FTTP network so large? The NBN Corporate plan provides no detailed information on its financial modelling, but it states that an all-FTTP network would take until 2026 to 2028 to complete.
If the timeframe was indeed as long as this, the revenue stream would be delayed. This could indeed lead to unrealistically large numbers for the peak funding cost of FTTP.
So where does the 2026 to 2028 timeframe come from? My guess is that NBN Co has simply extrapolated from the present rollout rate for FTTP, which has not increased much since 2013. One piece of supporting information comes from a Senate Estimates meeting, where NBN Co confirmed that its $74-84 billion number was not for a “continued” FTTP network but for a “restart” from the current plan.
NBN Co waited until September this year to hire additional staff, increasing the number of employees from 3,400 to 4,500 to speed up the rollout of FTTN. If it had hired these additional staff in 2013 and focused on the FTTP rollout, the network could well have been completed by around 2020 or 2021.
This article originally appeared on The Conversation
Comments
7 responses to “What Will The NBN Really Cost?”
I’m kind of over the NBN now and the whole faster Internet. It’s been a complete balls up since Lib took over. Lab was going to basically rip out all copper and replace with fibre (still the best idea) and now with the leaks coming think and fast, it looks like Libs have to do the same but they are putting copper back in
Somehow i told you so… just doesnt quite say it…
“The federal government’s strategic review of the NBN put the cost of remediating the copper at $2685 per node, but the leaked documents, sighted by iTnews, reveal NBN expects this will in reality sit at $26,115 per node.”
http://www.itnews.com.au/news/nbn-facing-massive-copper-remediation-bill-412595
So when will Malcolm be held responsible for this all mighty cockup?
It is an infrastructure that makes money in the long run. Let’s business be competitive, allows cloud based systems and backups to become feasible with fast uplink speeds, and helps create new businesses that didn’t exist before, and will save money and time with remote conferencing for medical issues etc.
It is an investment, one that will likely pay itself back many times over.
My solution uses the best of both worlds. Leave HFC in and worry about it at the end, but for the rest, roll out fibre to the drop point.
It has the advantages of FttN, by avoiding what makes FttP expensive – the stretch from the curb into the house – but makes the copper still in play so much shorter that you get FttP type speeds.
Short summary is rolling fibre up and down every street, ala FttP, but putting a node for each house in the small Telstra pits you see every 2nd or 3rd house. Brick sized nodes, easily replacable, and the cost of rolling from there to the home shouldnt be any more than a new phone connection.
Its where Telstra builds from after all. You already have the plans prepared, Labor’s FttP plans have done all the hard figuring already, so theres no prep time needed.
You end up with 10-20m of copper, which is short enough to get speeds into the hundreds of Mbps, and good enough for a couple of decades, adding longevity to things, a thing FttN is sorely missing. As houses want to upgrade to full FttP and take advantage of the future 1 Gbps speeds, let them.
Of course, thats practical, so nobody will consider it.
This hasn’t factored in ongoing costs. Of which there are two important ones:
1. Maintenance
2. Obsolescence
Fibre, may be more expensive to install, but it scores reasonably well on the two points above. Baring physical damage (trees across lines) fibre doesn’t corrode or degrade. And speeds in the multiple gigabit level are very much feasible.
HFC is a curate’s egg. It’s very prone to noise/interference and performs poorly in hot weather. Optus’s network is only just fit for purpose, and Telstra’s requires a lot of ongoing repairs to remain functional. That said, if properly maintained, the newer DOCSIS standards would allow for significant speed increases on cable.
Copper is just bad all round. The existing network requires massive investment of effort and money just to keep it operational on a day-to-day basis. Much of the cabling is decades old and corroded. The real kicker is that signal degradation will always result in a losing trade off between cable length and speed. Anything more than 100m will never get much above current ADSL speeds. Anything less and it would probably be cheaper in the long run just to replace the lot with fibre.
… my sanity …